Discuss other potential problems that can occur from the improper use of standard costs.

Discuss other potential problems that can occur from the improper use of standard costs.

Question 1

Having Trouble Meeting Your Deadline?

Get your assignment on Discuss other potential problems that can occur from the improper use of standard costs. completed on time. avoid delay and – ORDER NOW

Perform an Internet search using the phrase “reducing overhead costs”. Select and read a case study or article from the results of your search. (Make sure that you do not select an instructor’s lecture notes or a class assignment from the results of your search.) Summarize the case study or article, and relate the ideas of the article to what you have learned this week in this course.

Citation included

Question 2

There are several potential problems that can occur from the improper use of standard costs. Labor quantity standards and efficiency variances assume that production is labor-paced. However, output in many companies is determined by the processing speed of machines. Also, too much emphasis on meeting the standards may overshadow other important objectives. Discuss other potential problems that can occur from the improper use of standard costs.

Citation Included

.
Lion Company’s direct labor costs for the month of January were as follows:

What was Lion’s direct labor efficiency variance? (Points : 2)

$6,000 favorable

$6,150 favorable

$6,300 favorable

$6,450 favorable

Question 2.2. Information on Rex Co.’s direct material costs for May follows:
For the month of May, what was Rex’s direct materials price variance? (Points : 2)

$2,800 favorable

$2,800 unfavorable

$6,000 unfavorable

$6,000 favorable

Question 3.3. Buckler Company manufactures desks with vinyl tops. The standard material cost for the vinyl used per Model S desk is $27.00 based on 12 square feet of vinyl at a cost of $2.25 per square foot. A production run of 1,000 desks in March resulted in usage of 12,600 square feet of vinyl at a cost of $2.00 per square foot, a total cost of $25,200. The materials quantity variance resulting from the above production run was: (Points : 2)
$1,200 unfavorable

Explanation & Answer

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Order Now and we will direct you to our Order Page at Litessays. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?

Similar Posts